Hagerty Hall
Hagerty Hall
Herrick Archives Number 037
A. IDENTIFICATION & LOCATION
1. Name
1.1 Officially named "Hagerty Hall" by Board of Trustees on March 3, 1947.
1.2 Alternate names noted:
College of Commerce and Journalism Building
Commerce Building
See Addendum No. 2
2. Location
2.1 Located at 1775 College Road. Originally 1775 South College Road. Also, 93 South Oval Drive used as address for fire vehicles only.
2.2 For greater detail, see Sheet 98 in the book of campus maps in the University Archives.

For identification of other buildings shown, see Appendix A.
3. General Description
3.1 Type of construction:
Reinforced concrete frame with brick exterior.
3.2 No. of stories:
Basement and 4 floors
3.3 Increments of construction:
Enlarged once. See sketch.
See Addendum No. 4.

A-Original Building
B-Addition
C-Transformer vault built as part of addition
D-Light courts
3.4 Present area of building as shown in inventory records of Division of Campus Planning:
135,901 sq. ft. gross; 76,024 sq. ft. net assignableSee Addendum No. 1
3.5 Volume of building:
1,904,500 cu. ft. (PP)
B. PLANNING & CONSTRUCTION—ORIGINAL BUILDING
1. On July 5, 1922 the Board of Trustees approved the plans and related documents prepared by Joseph N. Bradford and authorized the solicitation of bids by contractors.
2. Bids were received on September 7, 1922 (McC4:6).
3. On September 8, 1922 the Board of Trustees awarded contracts to the following contractors:
General: E. H. Latham
Electrical: E. H. Cobb
Plumbing, heating and ventilating: Huffman-Wolfe Co.
4. Beginning of work:
Excavation was started in mid-October, 1922. (L:1/9/23)
5. Completion and occupancy:
5.1 The Board of Trustees accepted the building from the general contractor on July 17, 1924 (T) . However, this action was based on a June 4, 1924 letter from the University Architect to the Secretary of the Board of Trustees (McC4;132), which would indicate that the building was completed by the beginning of June, 1924.
5.2 The building was first used in the Autumn Quarter of 1924 (R 24-25:11).
C. PLANNING & CONSTRUCTION—ADDITION
1. On June 14, 1948 the Board of Trustees approved the plans and related documents prepared by Bellman, Gillett and Richards and authorized the solicitation of bids by contractors.
2. Bids were received on August 31, 1948 (T) .
3. On September 7, 1948 the Board of Trustees awarded contracts to the following contractors:
General: Haig M. Boyajohn
Electric wiring and fixtures: Electrical Contractors, Inc.
Heating: T. J. Connor, Inc.
Plumbing: Sauer Co.
Elevator: Otis Elevator Co.
4. Beginning of work:
5. Completion and occupancy:
5.1 Completed in Spring of 1950 (R 49-50:23).
5.2 Scheduled to be ready for students in Autumn Quarter of 1950 (L:5/31/50).
6. Dedication:
D. COST
Listed at $352,508.07 as of June 30, 1926; at $1,522,862.69 as of June 30, 1951; and at $1,938,286.73 as of June 30, 1971 (B).
E. PHOTOGRAPHS
1. In Photoarchives:
X 7760 Original Building
X 7761 Original Building
X 7762 Addition
X 7763 Addition
2. Other:
McC4:132
R 48-9:31
John H. Herrick
August 27, 1976
ADDENDUM NO. 1
Campus Planning records now show the following areas for this building:
137,019 sq. ft. gross
74,849 sq. ft. net assignable
John H. Herrick
February 7, 1985
ADDENDUM NO. 2
This building is now carried in Campus Planning records as James E. Hagerty Hall. The official name remains "Hagerty Hall."
John H. Herrick
August 26, 1986
Additional Hagerty Hall Addenda
ADDENDUM NO. 3
With the move of the Fisher College of Business to new facilities, Hagerty Hall was gutted and renovated to accommodate the College of Humanities.
The Board of Trustees approved capital budget recommendations for the renovation of Hagerty Hall in the amount of $18.5 million on July 11, 1997. Trustees authorized the university to seek construction bids February 5, 1999.
The architects were Wandel & Schnell Architects, Inc. in collaboration with Leers Weinzapfel Associates. Miles-McClellan Construction Co. was the general contractor. The renovation was completed in 2005, with a grand re-opening event on January 10, 2005.
Lorrie A. McAllister, Knowlton School of Architecture
Jan. 23, 2006
ADDENDUM No. 4 - PLANNING AND CONSTRUCTION - REHABILITATION
DESCRIPTION
1. This addendum expands upon Addendum No. 3
2. This project was to rehabilitate the entire building, including building system replacement and complete redesign of the interior spaces to house a portion of the College of Humanities
3. According to the Columbus Dispatch on March 6, 2004, the renovation was three months behind schedule due to previously unidentified hazardous materials. This increased the price of the project by $1.5 million.
4. According to The Lantern on January 5, 2005, Hagerty Hall opened on January 3, 2005. The renovation included a World Media Center, a cafe, new 250 seat auditorium, state of the art classrooms and labs, a video conferencing center and a renovated courtyard.
The building now houses the College of Humanities and most of the universities language departments.
SIGNIFICANT DATES
1. The architect/engineer contract was awarded on March 6, 2000.
2. The schematic design approval was on May 1, 2001.
3. The design development document approval was approved on December 20, 2001.
4. Construction document approval was on August 2, 2002.
5. Bid opening occurred for different project requirements.
5.1 Bid opening (Demo/Asbestos Abatement) on August 8, 2002.
5.2 Bid opening (Main building package) on August 8, 2002.
6. Construction began at multiple stages.
6.1 Construction Began on October 21, 2002.
6.2 Construction (main building package) began on March 3, 2003.
7. Report of awards to the Board of Trustees on March 5, 2003.
8. The date of completion was on October 1, 2004.
MISCELLANEOUS
DESIGN AND CONSTRUCTION
1. University associates who worked on the project include:
Project Manager: Scott Conlon
2. Design: Wandel & Schnell Columbus, Ohio
3. The Board of Trustees awarded contracts to the following contractors.
Demolition: American Services Group Inc., Cleves, Ohio $740,000
Asbestos Abatement: Keen and Cross, Inc, Granville, Ohio $227,937
General: Miles-McClellan Company, Columbus, Ohio $8,364,000
Plumbing: Aggressive Mechanical Inc, Columbus, Ohio $1,139,000
HVAC: Farber Corporation, Columbus, Ohio $4,289,000
Electric: Gaylor Group Inc. Dublin, Ohio $2,232,611
COST
1. The budget for the project was $24,327,569.77
Anthony Killian
KSA Digtial Library Assistant
April 22, 2010
Photo Addendum from KSA Digital Library
-
Aerial view
-
Aerial view
Media Asset Year:1947
-
Aerial view
Date Comment:Not dated
-
Exterior view
Media Asset Year:2007
-
Exterior view from Oval
Media Asset Year:1939
-
Exterior view from southeast
Media Asset Year:1953
-
Interior view of auditorium
Date Comment:October 18, 1962
-
Interior view of main hall, 1927
Media Asset Year:1927
-
Site plan
-
Sketch
-
View during renovation
Media Asset Year:2003
-
View during renovation
Media Asset Year:2003
-
View from Oval
Date Comment:no date
-
View of addition from northeast
Media Asset Year:1950
-
View of addition from south
Date Comment:None given
no date (after 1950)